Moses Lake Shoreline Protection
Project Overview
Project Location
Moses Lake @ NE side of TX St Hwy 146
Galveston County, Texas 77590
Owner
Galveston Bay Foundation
Construction Dates
Start: 02/12/2018
Finish: 08/07/2018
Contract amount
$1,889,830.00
This project encompassed the civil construction of the Moses Lake Shore Protection, Phase III, located along State Highway 146 in Galveston Bay. The scope of work included constructing 5,970 linear feet of breakwater, three Oystercatcher nesting areas, and 190 linear feet of sill. Utilizing imported riprap and toe protection stone, the construction was designed to ensure long-term stability and durability of the shoreline protection measures, adhering to detailed technical specifications.